This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
module:purchaseorder:purchasingorder:list [2014/08/28 18:50] target |
module:purchaseorder:purchasingorder:list [2014/12/10 23:23] (current) target |
||
---|---|---|---|
Line 19: | Line 19: | ||
Purchase Order (PO) | Purchase Order (PO) | ||
+ | |||
can be: | can be: | ||
+ | |||
- PO acts as a request for quotation until approved by project manager | - PO acts as a request for quotation until approved by project manager | ||
+ | |||
- an approved PO is a formal form use to justify ordered materials given set of conditions | - an approved PO is a formal form use to justify ordered materials given set of conditions | ||
Line 55: | Line 58: | ||
c.2. discuss quotation with the assigned PM (pm will either approve or disapprove) | c.2. discuss quotation with the assigned PM (pm will either approve or disapprove) | ||
- | c.3. provider | + | c.3. provide |
c.4. finalize PO (send an approved/ | c.4. finalize PO (send an approved/ | ||
Line 62: | Line 65: | ||
c.6. proceed to creating Transfer Job Order; see [[module: | c.6. proceed to creating Transfer Job Order; see [[module: | ||
+ | |||
+ | **When to create a Transfer JO for Purchasing Order:** | ||
+ | |||
+ | Transfer JO is needed when supplier informs purchasing that PO Qty is ready for pick-up or deliver; at this point purchasing is required to create a Transfer JO - Purchasing type indicating the items that will be received or need to be picked-up. Works like JO-Receiving but for local details of incoming shipment. | ||
**D. Re-Ordering a For Revision Purchase Order** | **D. Re-Ordering a For Revision Purchase Order** | ||
+ | |||
note: re-ordering means changing for revision status PO to Ordered status upon consideration of change in purchase request quantity as well as informing suppliers about the revised orders provided with revised formal PO. | note: re-ordering means changing for revision status PO to Ordered status upon consideration of change in purchase request quantity as well as informing suppliers about the revised orders provided with revised formal PO. | ||
- | d.1. select a For Revision PO you want to re-order | + | points to consider: |
+ | |||
+ | * quantity of items to add/deduct from approved order | ||
+ | |||
+ | * timing of revision (status of orders/ | ||
+ | |||
+ | * preference of supplier with regards in changing of orders/PO | ||
+ | |||
+ | upon consideration you may proceed by: | ||
+ | |||
+ | d.1. select a "For Revision" | ||
+ | |||
+ | d.2. discuss with supplier about the revision | ||
- | d.2. check for revision of PO Qty - enter new PO qty if any | + | d.3. check for possible |
- | d.3.a if no changes made click " | + | d.4.a if no changes made click " |
- | d.3.b if with changes, | + | d.5.b if with changes, |
- | **d.3.b (option 1: revise previously approved PO)** | + | **d.5.b (option 1: revise previously approved PO)** |
- | d.3.b.1 discuss | + | d.5.b.1 resend printed PO with revised quantity (using re-printed or previously signed PO) as agreed in discussion |
- | d.3.b.2 resend printed PO with revised quantity (using re-printed or previously signed PO) as agreed in discussion | + | d.5.b.2 follow section **C. Confirming a Purchase Order** c.1 to c.4 |
- | d.3.b.3 follow section **C. Confirming a Purchase Order** c.1 to c.4 | + | d.5.b.3 update PO Qty base on the total approved quantity in PO (previously approved Qty +/- revision) |
- | d.3.b.4 update | + | d.5.b.4 click " |
- | d.3.b.5 click " | + | d.5.b.5 proceed |
- | **d.3.b (option 2: consider a new PO for additional order/s)** | + | **d.5.b (option 2: consider a new PO for additional order/s)** |
- | d.3.b.1 click " | + | d.5.b.1 click " |
- | d.3.b.2 follow section A,B & C to order additional PO qty | + | d.5.b.2 follow section A,B & C to order additional PO qty |
**System Record Status:** | **System Record Status:** |